Above-ground vertical DWV
One piece, no sliding parts. Fernco Expansion Joints take up the movement in a vertical DWV stack so you don’t have to build an offset to do it. Now 1½″ through 6″.
Why it exists
Temperature swings make DWV piping grow and shrink. In a vertical stack that movement has to go somewhere, and the traditional answer is an expansion offset built out of fittings. An expansion joint takes the movement at a single point instead, in a connection that clamps on with standard tools.
A molded elastomeric PVC body with two stainless clamps. Nothing telescopes, so there is no packing to bind, freeze or weep years after the walls close.
Movement is handled at the joint rather than by a run of fittings turned out of the chase and back. Fewer joints, less labor, and the stack stays where the riser diagram put it.
Pipe ends insert to internal stops for positive positioning. Tighten both stainless clamps to 60 in-lb with standard tools, or 120 in-lb on the XJ-6, which uses a high torque band.
Travel
The joint installs at a normal position of 4.00″ face to face. From there it takes up 1½″ of expansion and ½″ of contraction, so a section has to be sized for movement in both directions, not just the hot case.
Pipe colder than when it was installed. The body draws up as the pipe ends pull apart. ½″ available.
How it goes in: 4.00″ face to face, with travel left in both directions.
Pipe hotter than when it was installed. The body compresses as the pipe grows into it. 1½″ available.
Normal position, face to face
Expansion available from normal
Contraction available from normal
in-lb clamp torque, both bands. XJ-6 has a high torque band and takes 120.
The joint does not support the stack. Brace the piping to suit the building, so it is carried and held in alignment without restricting its movement. Set the joint at its normal position before tightening, and remember that a stack installed on a very hot or very cold day may already be part-way through its travel.
Put movement in perspective
Enter the pipe material, the length of the section between anchors and the temperature swing you expect. This gives the movement for that section and compares it against what one joint can take up.
Enter a length and a temperature change.
This is a sizing aid, not a design. Joint locations, supports and guides are set by the applicable plumbing code, the project design and the pipe manufacturer’s published data.
Worked example from the published coefficients: a 30-foot section of PVC grows roughly ⅔″ with a 60°F rise. The same section in standard ABS grows roughly 1.2″. Plastic pipe moves roughly five to nine times as much as cast iron or steel.
| Material | Coefficient (in/in/°F) | Movement per 100 ft per 10°F |
|---|---|---|
| PVC DWV | 3.0 × 10-5 | about 0.36″ |
| ABS DWV | 5.5 × 10-5 | about 0.66″ |
| Cast iron | 5.9 × 10-6 | about 0.07″ |
| Steel | 6.5 × 10-6 | about 0.08″ |
Sizes
Ranges cover Schedule 40 plastic and steel at every size, and cast iron no-hub and cast iron service weight at 2″ and larger. Check the measured outside diameter of the pipe against the range rather than going by nominal size alone.
| Part No. | Nominal pipe size | Fits pipe O.D. | Clamp torque | Carton qty | Weight |
|---|---|---|---|---|---|
| XJ-150 | 1½″ (38 mm) | 1.65 – 2.00″ | 60 in-lb | 20 | 0.38 lb |
| XJ-2 | 2″ (50 mm) | 2.15 – 2.50″ | 60 in-lb | 20 | 0.47 lb |
| XJ-3 | 3″ (76 mm) | 3.15 – 3.70″ | 60 in-lb | 20 | 0.61 lb |
| XJ-4 | 4″ (102 mm) | 4.10 – 4.65″ | 60 in-lb | 20 | 0.75 lb |
| XJ-6 NEW | 6″ (152 mm) | 6.30 – 6.80″ | 120 in-lb | 6 | 2.93 lb |
All five install at the same 4.00″ normal position and take up the same 1½″ expansion and ½″ contraction. XJ-6 uses a high torque band and is tightened to 120 in-lb, double the 60 in-lb used on XJ-150 through XJ-4. Listing scope: ICC-ES PMG-1117 covers XJ-150 through XJ-4. XJ-6 is not on that listing, so confirm acceptance with the code official before specifying it on a project that requires one.
Where it goes
Expansion joints belong in vertical above-ground DWV stacks and inside rainwater conductors, where a long riser passes through floors and the pipe has room to grow between supports.
Choosing
Thermal movement in a stack gets absorbed one of three ways. Which one belongs on the job depends on the space in the chase, what the specification calls for, and how much labor the offset would cost.
You are here
The alternative
The alternative
Short version: if the chase has room and the run is short, an offset may be the cheaper answer. If the stack is tall, the chase is tight, or the schedule cannot absorb building offsets floor by floor, the joint is doing the same job in one fitting’s worth of space.
Ratings and specifications
Elastomeric PVC body with 300 series stainless steel clamp bands. XJ-6 uses a 316 series high torque band.
| Gasket | Elastomeric PVC to ASTM D5926, Shore A 65 ±5 |
| Clamp bands | 300 series stainless steel. XJ-6: 316 series high torque band. |
| Installation torque | 60 in-lb. XJ-6: 120 in-lb. |
| Tensile strength | 1000 psi minimum |
| Elongation at rupture | 250% minimum |
| Tear strength | 150 lb/in. minimum |
| Brittleness temperature | −40°F |
| Application | Above-ground vertical DWV and rainwater conductors |
| Movement | 1½″ expansion, ½″ contraction from a 4.00″ normal position |
| Maximum test pressure | 4.3 psi |
| Maximum operating temperature | 140°F intermittent. No continuous rating published. |
| Fits | Plastic, cast iron and steel pipe |
Installation
The whole install happens in the line with standard tools. Full instructions ship with the product and are in the documents below.
Loosen both clamps
Insert pipe to the stops
Set the normal position
Torque to 60 in-lb (120 in-lb on XJ-6)
Brace and test
Before it is concealed: brace the piping independently of the joint, without restricting its movement, confirm the joint is sitting at its normal position rather than already part-way through its travel, and leak test the system.
Codes and compliance
Everything a plan reviewer or a code official is going to ask for, in one place.
| ICC-ES PMG-1117 | To ASTM C1173 and CSA B602. Covers XJ-150 through XJ-4. Above-ground use is subject to the approval of the code official. |
| ASTM C1173 | Flexible transition couplings for underground piping systems |
| CSA B602 | Mechanical couplings for drain, waste and vent pipe and sewer pipe |
| ASTM D5926 | Gasket, per Fernco published data |
| Specify under | CSI 22 05 16 |
Sell sheet with the full part table, technical data and the stack installation illustration.
One drawing per part, for submittals and spec packages.
1½″ of expansion and ½″ of contraction, measured from the 4.00″ normal position it installs at. Contraction is the tighter of the two, so size the section for the cold case as well as the hot one.
Go by the measured outside diameter of the pipe, not the nominal size. XJ-150 fits 1.65 to 2.00″, XJ-2 fits 2.15 to 2.50″, XJ-3 fits 3.15 to 3.70″, XJ-4 fits 4.10 to 4.65″ and XJ-6 fits 6.30 to 6.80″. The ranges cover Schedule 40 plastic and steel at every size, and cast iron no-hub and service weight at 2″ and larger.
That comes out of the design rather than a rule of thumb. Work out the expansion and contraction for each section between anchors using the pipe manufacturer’s published coefficients, compare it with the travel available at the joint, and shorten the section or add joints if it does not fit. The calculator above does the arithmetic for a single section.
No. These are for vertical, above-ground DWV stacks and inside rainwater conductors. They are not a buried fitting and not a pressure fitting; maximum test pressure is 4.3 psi.
No. Pipe bracing, consistent with the building, carries the piping and keeps it in alignment, and it must not restrict the pipe’s movement. The joint only absorbs movement, and a stack that leans on it will not behave the way the design assumed.
XJ-150 through XJ-4 are covered by ICC-ES PMG-1117 to ASTM C1173 and CSA B602, and above-ground use is subject to the approval of the code official. The gasket conforms to ASTM D5926 per Fernco published data. The new XJ-6 is not on that listing yet, so confirm acceptance before specifying it where a listing is required.
140°F intermittent. Fernco publishes this as non-continuous, and there is no continuous rating. Brittleness temperature is −40°F at the cold end.
Yes. On a very hot or very cold day the pipe may already be part-way expanded or contracted as it acclimates, which changes how much travel is left in each direction. Set the joint at its normal position and account for the installation temperature when you calculate movement.
Tell us the pipe size and material, the section lengths and the temperature range, and our technical group will help you work through joint placement.